Get Ready to Pass the C-TS412-1909 exam with SAP Latest Practice Exam [Q11-Q35]




Get Ready to Pass the C-TS412-1909 exam with SAP Latest Practice Exam

Get Prepared for Your C-TS412-1909 Exam With Actual SAP Study Guide!


SAP C-TS412-1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.


SAP C-TS412-1909 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Configure cost center reporting and create report painter reports
  • Describe how the Resource Planning process integrates with HCM
Topic 2
  • Determine general reporting requirements and reporting requirements for cost centers
  • ame the components of Work Breakdown Structure, Network and activities, Milestones
Topic 3
  • Revenues and Payments, Reporting, Project Structures
  • Describe the importance of various dates which can be tracked for projects
Topic 4
  • Describe procedures for establishing budgets and reporting costs
  • Describe the characteristics of Revenues & Payments
Topic 5
  • Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement

 

NEW QUESTION 11
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.

 
 
 
 
 

NEW QUESTION 12
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?

 
 
 
 

NEW QUESTION 13
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 14
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

 
 
 
 
 

NEW QUESTION 15
What could be a reason to use expert mode in the valuation method for results analysis?

 
 
 
 

NEW QUESTION 16
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

 
 
 
 

NEW QUESTION 17
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?

 
 
 
 

NEW QUESTION 18
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?

 
 
 
 

NEW QUESTION 19
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.

 
 
 
 

NEW QUESTION 20
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?

 
 
 
 

NEW QUESTION 21
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.
What controls whether the delivery date is defined by the earliest or latest scheduled dates?

 
 
 
 

NEW QUESTION 22
Which statement is valid regarding networks?

 
 
 
 

NEW QUESTION 23
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However,
the duration did not changed after overall network scheduling. What do you check? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 24
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.

 
 
 
 

NEW QUESTION 25
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 26
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

 
 
 
 

NEW QUESTION 27
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.

 
 
 
 

NEW QUESTION 28
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.

 
 
 
 

NEW QUESTION 29
Which object is used to allocate the costs from a claim to the project structure?

 
 
 
 

NEW QUESTION 30
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements.
What planning method for basic dates do you use ?

 
 
 
 

NEW QUESTION 31
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question

 
 
 
 

NEW QUESTION 32
You have saved a network and activates with assigned material components. As soon as you release the network,
you receive the error message “Business transaction cannot be carried out” What could be the reason for this error message?

 
 
 
 

NEW QUESTION 33
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.

 
 
 
 

NEW QUESTION 34
Your customer’s projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?

 
 
 
 

NEW QUESTION 35
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.

 
 
 
 


C-TS412-1909 Exam Certification Details:

Cut Score:51%
Exam:80 questions
Duration:180 mins
Languages:English

 

Pass Your Next C-TS412-1909 Certification Exam Easily & Hassle Free: https://www.exams4sures.com/SAP/C-TS412-1909-practice-exam-dumps.html