SAP C_TS412_1909 Exam Prep Guide Prep guide for the C_TS412_1909 Exam [Q62-Q86]




SAP C_TS412_1909 Exam Prep Guide: Prep guide for the C_TS412_1909 Exam

2022 New Preparation Guide of SAP C_TS412_1909 Exam

Q62. You have created an internally-processed network activity, and assigned a work center and the work. After saving,
you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question

 
 
 
 
 

Q63. Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

 
 
 
 

Q64. You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

 
 
 
 
 

Q65. Where can you define a network as “header-account-assigned” or “activity-account-assigned”?

 
 
 
 

Q66. A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.

 
 
 
 
 

Q67. A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

 
 
 
 

Q68. Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?

 
 
 
 

Q69. COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?

 
 
 
 

Q70. Your customer’s projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?

 
 
 
 

Q71. How can you grant individual authorization for WBS elements and networks?

 
 
 
 

Q72. Which object is used to allocate the costs from a claim to the project structure?

 
 
 
 

Q73. Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

 
 
 
 
 

Q74. To which object can you assign a factory calendar?

 
 
 
 

Q75. In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

 
 
 
 

Q76. Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.

 
 
 
 

Q77. Revenues & Payment
A customer use cross- company – code project with a top billing element and additional billing element underneath (por debajo) for each company code. Although the internal ..
correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?

 
 
 
 

Q78. You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?

 
 
 
 

Q79. You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.

 
 
 
 

Q80. Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?

 
 
 
 

Q81. Materials
Your customer use a tight (estrecha) integration between sales order and WBS with network to deliver finished and semi-finish product.
What benefit do they have when using delivery from project (CNSO).

 
 
 
 

Q82. How can you record external service activities with service master data? Note: There are 2 correct answers to this question

 
 
 
 

Q83. How can you confirm the working hours of different work centers for a single activity?

 
 
 
 

Q84. Dates
How are earliest dates and latest dates of activities schedule?

 
 
 
 

Q85. You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling.
What do you recommend for milestone definition?

 
 
 
 

Q86. You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

 
 
 
 

Latest Questions C_TS412_1909 Guide to Prepare Free Practice Tests: https://www.exams4sures.com/SAP/C_TS412_1909-practice-exam-dumps.html

Post date: 2022-11-04 09:12:53
Post date GMT: 2022-11-04 09:12:53
Post modified date: 2022-11-04 09:12:53
Post modified date GMT: 2022-11-04 09:12:53